Monday 29 January 2018

SOFTWARE PROJECT MANAGEMENT




Which of the following describes RFP?
Select one:
Requirements for a Project issued by the customer
Request for Project issued by vendor
Request for Proposal issued by the customer
Requirements for Proposal prepared by vendor 
The correct answer is: Request for Proposal issued by the customer
Question 2
The following closely resembles a software contract
Select one:
Purchase Order issued by the customer
MoU between customer and vendor 
Legal document containing Terms & Conditions
Requirements document prepared by customer
The correct answer is: MoU between customer and vendor

Question 3
The ownership of software developed in a typical project with T&M model rests with
Select one:
Vendor
Customer 
Jointly shared between customer and vendor
Escrow agency
The correct answer is: Customer

Question 4
Limited Tendering process is normally used for
Select one:
Select projects with unique technology
Maintaining confidentiality 
Eliminating competition
Identifying and eliminating weak vendors

The correct answer is: Select projects with unique technology
Question 5
The primary goal of agile methodology is
Select one:
Reduce documentation overhead
Produce time-to-market products/services
Develop product in close collaboration with customers
All the mentioned 

The correct answer is: All the mentioned

Question 6
The following is one approach for Risk Transfer in projects
Select one:
Buy insurance from third-party agencies
Distribute risk equally between customer and vendor
Customer managing risk
All the mentioned 
Feedback
Your answer is incorrect.
The correct answer is: Buy insurance from third-party agencies

Question 7
Function Point (FP) Method of estimation is best used when
Select one:
Actual size of the final code (SLOC) is not known
Requirements are unclear 
Technology/Development Tools are not yet known
Water-Fall Model is adopted as development methodology

The correct answer is: Technology/Development Tools are not yet known
Question 8

SCRUM Meetings are conducted in one of the variations of
Select one:
Rapid Prototyping model
Agile Model 
Incremental & Iterative Model
All the mentioned

The correct answer is: Agile Model


Question 9
The key role of Program Manager is one of
Select one:
Resource Leverage across projects
Escalation point above Project Manager
Project Information Reporting to Steering Committee 
Relationship Management with customer

The correct answer is: Resource Leverage across projects

Question 10
The major goal of RAD model of development is
Select one:
Reduce cost of development and time
Identify erroneous requirements early in the project 
Prototype development before undertaking investment
Avoid Risk Management
The correct answer is: Reduce cost of development and time

Question 11
Identification of regulatory standards for development is done during
Select one:
Requirements analysis
Contract preparation
Quality Planning
All the mentioned 
The correct answer is: All the mentioned

Question 12
Requirements for Proposal is prepared by
Select one:
Vendor as self-assessment of its capabilities
Customer as part of investigating vendor potential
Third-party agency to assess credit-worthiness of customer 
Customer during the closure of the project
.
The correct answer is: Customer as part of investigating vendor potential

Question 13
Assignment of People to  activities in projects is done during the following phase
Select one:
Activity Planning
Resource Scheduling 
Skill Assessment
Project Monitoring & Control
The correct answer is: Resource Scheduling


Question 14
Warranty Maintenance of product commences when
Select one:
Acceptance and Delivery of the product is completed 
Integration Testing is complete
A separate Maintenance contrast is issued by the customer
Defects start surfacing in the delivered product
The correct answer is: Acceptance and Delivery of the product is completed

Question 15
Going by the experience of many IT projects in India, Fixed-Price Contracts are mostly advantageous to
Select one:
Customer 
Vendor
Risk Manager
Finance Manager
The correct answer is: Customer

Question 16
The following tool can be used for Project Status Reporting
Select one:
GANTT chart
MS-Excel
MS-Project
All the mentioned 
The correct answer is: All the mentioned

Question 17
Risk Analysis is done in Sprial Model of development after
Select one:
Every iteration
Requirements phase 
System Testing
All the mentioned
The correct answer is: Every iteration

Question 18
Software Product Quality is primarily determined by
Select one:
No. of Defects reported
Usability 
Schedule/Cost overrun
Marketability
The correct answer is: No. of Defects reported







Question 19
The role of Project Steering Committee is
Select one:
a. Escalation mechanism setup by the customer
b. Govern day-to-day operations of the project 
c. High-level monitoring of the project by key stakeholders
d. Report project status to the CEO
The correct answer is: High-level monitoring of the project by key stakeholders


Question 20
Critical Path in a project activity network diagram indicates
Select one:
Chain of activities requiring common resources
Path of least resistance to delay
Activities whose resources cannot be scheduled late
Activities which have zero or minimum float 

The correct answer is: Activities which have zero or minimum float

Question 21
Contingency measures in Risk Planning are provided for
Select one:
Preventing potential risks identified early on
Reduce the probability of occurrence of risk events 
Reducing the impact of risk should it occur
Minimizing the cost of risk mitigation activities
The correct answer is: Reducing the impact of risk should it occur

Question 22
To shorten the duration of a project, the following can be done
Select one:
Reducing the duration of activities on critical path
Eliminating non-critical activities 
Providing more resources to activities with large float
By employing critical-chain analysis
The correct answer is: Reducing the duration of activities on critical path

Question 23
The following method of project monitoring is more appropriate for T&M projects
Select one:
Weekly or Monthly review
Milestone based 
Decision-point based
Upon acceptance criteria
The correct answer is: Weekly or Monthly review

Question 24
Earned Value Analysis (EVA) helps in
Select one:
Cost-monitoring of project
Monitoring of schedule overruns
Monitoring of cumulative effort overrun
All the given options are correct. 

The correct answer is: All the given options are correct.
Question 25
COCOMO II is a software estimation tool based on
Select one:
Parametric method of cost estimation 
Function-point analysis of size
Analogical reasoning of past projects
Euclidian distance between similar projects
The correct answer is: Parametric method of cost estimation


No comments:

Post a Comment