SOFTWARE PROJECT MANAGEMENT
Which of the following describes RFP?
Select one:
Requirements for a Project issued by the customer
Request for Project issued by vendor
Request for Proposal issued by the customer
Requirements for Proposal prepared by vendor
The correct answer is: Request for Proposal issued by the customer
Question 2
The following closely resembles a software contract
Select one:
Purchase Order issued by the customer
MoU between customer and vendor
Legal document containing Terms & Conditions
Requirements document prepared by customer
The correct answer is: MoU between customer and vendor
Question 3
The ownership of software developed in a typical project with T&M model rests with
Select one:
Vendor
Customer
Jointly shared between customer and vendor
Escrow agency
The correct answer is: Customer
Question 4
Limited Tendering process is normally used for
Select one:
Select projects with unique technology
Maintaining confidentiality
Eliminating competition
Identifying and eliminating weak vendors
The correct answer is: Select projects with unique technology
Question 5
The primary goal of agile methodology is
Select one:
Reduce documentation overhead
Produce time-to-market products/services
Develop product in close collaboration with customers
All the mentioned
The correct answer is: All the mentioned
Question 6
The following is one approach for Risk Transfer in projects
Select one:
Buy insurance from third-party agencies
Distribute risk equally between customer and vendor
Customer managing risk
All the mentioned
Feedback
Your answer is incorrect.
The correct answer is: Buy insurance from third-party agencies
Question 7
Function Point (FP) Method of estimation is best used when
Select one:
Actual size of the final code (SLOC) is not known
Requirements are unclear
Technology/Development Tools are not yet known
Water-Fall Model is adopted as development methodology
The correct answer is: Technology/Development Tools are not yet known
Question 8
SCRUM Meetings are conducted in one of the variations of
Select one:
Rapid Prototyping model
Agile Model
Incremental & Iterative Model
All the mentioned
The correct answer is: Agile Model
Question 9
The key role of Program Manager is one of
Select one:
Resource Leverage across projects
Escalation point above Project Manager
Project Information Reporting to Steering Committee
Relationship Management with customer
The correct answer is: Resource Leverage across projects
Question 10
The major goal of RAD model of development is
Select one:
Reduce cost of development and time
Identify erroneous requirements early in the project
Prototype development before undertaking investment
Avoid Risk Management
The correct answer is: Reduce cost of development and time
Question 11
Identification of regulatory standards for development is done during
Select one:
Requirements analysis
Contract preparation
Quality Planning
All the mentioned
The correct answer is: All the mentioned
Question 12
Requirements for Proposal is prepared by
Select one:
Vendor as self-assessment of its capabilities
Customer as part of investigating vendor potential
Third-party agency to assess credit-worthiness of customer
Customer during the closure of the project
.
The correct answer is: Customer as part of investigating vendor potential
Question 13
Assignment of People to activities in projects is done during the following phase
Select one:
Activity Planning
Resource Scheduling
Skill Assessment
Project Monitoring & Control
The correct answer is: Resource Scheduling
Question 14
Warranty Maintenance of product commences when
Select one:
Acceptance and Delivery of the product is completed
Integration Testing is complete
A separate Maintenance contrast is issued by the customer
Defects start surfacing in the delivered product
The correct answer is: Acceptance and Delivery of the product is completed
Question 15
Going by the experience of many IT projects in India, Fixed-Price Contracts are mostly advantageous to
Select one:
Customer
Vendor
Risk Manager
Finance Manager
The correct answer is: Customer
Question 16
The following tool can be used for Project Status Reporting
Select one:
GANTT chart
MS-Excel
MS-Project
All the mentioned
The correct answer is: All the mentioned
Question 17
Risk Analysis is done in Sprial Model of development after
Select one:
Every iteration
Requirements phase
System Testing
All the mentioned
The correct answer is: Every iteration
Question 18
Software Product Quality is primarily determined by
Select one:
No. of Defects reported
Usability
Schedule/Cost overrun
Marketability
The correct answer is: No. of Defects reported
Question 19
The role of Project Steering Committee is
Select one:
a. Escalation mechanism setup by the customer
b. Govern day-to-day operations of the project
c. High-level monitoring of the project by key stakeholders
d. Report project status to the CEO
The correct answer is: High-level monitoring of the project by key stakeholders
Question 20
Critical Path in a project activity network diagram indicates
Select one:
Chain of activities requiring common resources
Path of least resistance to delay
Activities whose resources cannot be scheduled late
Activities which have zero or minimum float
The correct answer is: Activities which have zero or minimum float
Question 21
Contingency measures in Risk Planning are provided for
Select one:
Preventing potential risks identified early on
Reduce the probability of occurrence of risk events
Reducing the impact of risk should it occur
Minimizing the cost of risk mitigation activities
The correct answer is: Reducing the impact of risk should it occur
Question 22
To shorten the duration of a project, the following can be done
Select one:
Reducing the duration of activities on critical path
Eliminating non-critical activities
Providing more resources to activities with large float
By employing critical-chain analysis
The correct answer is: Reducing the duration of activities on critical path
Question 23
The following method of project monitoring is more appropriate for T&M projects
Select one:
Weekly or Monthly review
Milestone based
Decision-point based
Upon acceptance criteria
The correct answer is: Weekly or Monthly review
Question 24
Earned Value Analysis (EVA) helps in
Select one:
Cost-monitoring of project
Monitoring of schedule overruns
Monitoring of cumulative effort overrun
All the given options are correct.
The correct answer is: All the given options are correct.
Question 25
COCOMO II is a software estimation tool based on
Select one:
Parametric method of cost estimation
Function-point analysis of size
Analogical reasoning of past projects
Euclidian distance between similar projects
The correct answer is: Parametric method of cost estimation